Setting a post for the greenhouse |
Getting ready to check level |
All posts concreted and curing |
We got lucky that the first week and a half of March was a dry week because Alvin was able to complete the grading required for our new greenhouses. We ran into a Spring so we were required to put drains between each house to drain the Spring water away from the greenhouses. It took us 3 weeks to dig post holes for our last greenhouse but this greenhouse we were able to have all the post holes dug and concreted in 2 and 1/2 days! That is a record for the earth on this farm. Normally we run into rocks in each hole that require us to pound the rocks out with a digging bar. |